The Project
Project Summary
Wooderson Solar Farm is located 40km south-west of Gladstone and 20km west of Calliope, in Central Queensland.
Wooderson Solar Farm’s location was chosen for its capacity for solar generation, proximity to transmission lines, accessibility and our ability to achieve the project goals with minimal environmental and community impacts.
The Project will consist of approximately 980,000 solar panels capable of generating 450 MW of electricity and associated infrastructure including access tracks, electrical reticulation cables, a substation and switching yard.
The Wooderson Solar Farm project will supply the National Electricity Market (NEM) with electricity generated from solar power. Key features include:
Solar PV Modules
980,000 solar PV modules, producing 450 MW of solar power.
Substation
An electrical substation and switching station.
Cable Reticulation
Overhead and underground electrical cable reticulation to connect the modules to the substation.
Irradiance Sensors
Sensors for measuring solar irradiance levels.
O&M Building
Operations and maintenance building with associated car parking.
Temporary Construction Facilities
Including a construction compound, borrow pit and concrete batching plant facilities.
Solar Farm Timeline
Site Selection & Feasibility
(12-18 mths)
Land identification
Constraints analysis and landowner mapping
Baseline environmental surveys
Initial non-intrusive site investigations, concept design and energy yields
Engagement with Traditional Owners and community reps
Construction & Commissioning (~29 mths)
Installation of solar PV modules and trackers
Construction of other project infrastructure including access tracks, substation, grid connection
Discharge planning and environmental conditions
Commissioning of solar farm
Grazing continues around constructed solar PV modules
Operations
(30-35 yrs)
Annual rental payments
Site managed by local operators
Grazing continues around the solar PV modules
Decommissioning (12 mths)
Development & Approval (12-16 mths)
Detailed site investigation and Project design work carried out
Irradiation assessment
Development Application materials prepared
Local community and key stakeholders consulted
Planning application submitted
Grid Connection Studies
(12-16 mths)
Analysis of connection options
Detailed design of substation and connection arrangement
Connection studies and assessment by AEMO and network provider
Financing & Further Site Investigations(12 mths)
Secure financing for the project
Sign contracts required to build the solar farm
Discharge planning and environmental conditions
Further site investigation works
Approvals
The website will be regularly updated as we progress through these key milestones for the Project.